[Important Information for Employees] Capital Projects Update
Magen Renadette
mrena002 at plattsburgh.edu
Thu Feb 20 13:58:58 UTC 2025
SENT ON BEHALF OF CAPITAL PLANNING & CONSTRUCTION
[image: image]
Capital Projects Update
[image: image]
[image: image]
[image: image]
[image: image]
Dining Facilities: "The Nest":
Project Complete: Grand Opening Held January 27, 2025
Algonquin Admission Center:
SUCF Project
Consultant: Architecture +
Design: January 2025 - January 2026
Bid Process: February 2026 - May 2026
Construction: June 2026 - June 2027
Demolition of Banks & Adirondack Halls:
SUCF Project
Consultant Selection: In Progress
Project Timeline: Concurrent with Algonquin Admission Center
Myers/Yokum Masonry Restoration:
SUCF Project
Bid Process: February 2025 - May 2025
Construction: June 2025 - June 2027
Note: Construction schedule includes winter shutdowns.
Infirmary HVAC Replacement:
Campus Let Project
Consultant: AES Northeast
Design: December 2024 - February 2025
Bid Process: March 2025 - May 2025
Construction: May 2025 - June 2025
Hudson Annex Replace (3) Rooftop Exhaust Fan Units:
Campus Let Project
Consultant: AES Northeast
Design: December 2024 - February 2025
Bid Process: March 2025 - May 2025
Construction: June 2025 - July 2025
Harrington Hall Lounge Improvements:
Campus Let Project
Consultant: Selection in Progress
Design: March 2025 - April 2025
Bid Process: April 2025 - May 2025
Construction: June 2025 - August 2025
Ward Hall Counseling Center Improvements:
Campus Let Project
Consultant: AEDA
Design: October 2025 - May 2025
Bid Process: June 2025 - August 2025
Construction Schedule: Capital Planning is Finalizing
Myers Recording Studio:
Campus Let Project: CREST Grant
Consultant: Hyman Hayes Associates
Design: March 2025 - August 2025
Bid Process: September 2025 - December 2026
Construction: January 2026 - May 2026
HTHW Replacement - Priorities 1 & 4:
Campus Let Project
Consultant: RMF Engineering
Design: April 2025 - September 2025
Bid Process: October 2025 - January 2026
Construction: May 2026 - October 2026
ADA Study - Campus Wide
Campus Let Project
Consultant Selection: In Progress
Capital Planning is committed to enhancing & improving our campus.
CAPITAL PLANNING & CONSTRUCTION
40 Sanborn Avenue
101 Broad Street
Plattsburgh, NY 12901
(o) 518-564-5052
plattsburgh.edu <https://www.plattsburgh.edu/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 13949 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 16523 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment-0001.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/png
Size: 61858 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 61391 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment-0002.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 325636 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250220/1aa2dc24/attachment-0003.jpe>
More information about the Critical-Employees
mailing list