[Important Information for Employees] Campus Capital Project Update
Magen Renadette
mrena002 at plattsburgh.edu
Thu Apr 17 17:00:29 UTC 2025
SENT ON BEHALF OF CAPITAL PLANNING & CONSTRUCTION
[image: image]
Capital Projects Update
[image: image]
[image: image]
[image: image]
[image: image]
Algonquin Admissions Center:
SUCF Project
Consultant: Architecture +
Design: January 2025 - January 2026
Bid Process: February 2026 - May 2026
Construction: June 2026 - June 2027
Demolition of Banks & Adirondack Halls:
SUCF Project
Consultant Selection: In Progress
Project Timeline: Concurrent with Algonquin Admissions Center
Myers/Yokum Masonry Restoration:
SUCF Project
Contractor: Murnane Building Contractors
Construction: June 2025 - June 2027
Note: Construction schedule includes winter shutdowns.
Infirmary HVAC Replacement:
Campus Let Project
Consultant: AES Northeast
Design: Complete
Bid Process: April 2025
Construction: July 2025 - August 2025
Hudson Annex Replace (3) Rooftop Exhaust Fan Units:
Campus Let Project
Consultant: AES Northeast
Design: Complete
Bid Process: April 2025
Construction: July 2025 - August 2025
Harrington Hall Lounge Improvements:
Campus Let Project
Consultant: AES Northeast
Design: March 2025 - April 2025
Bid Process: May 2025
Construction: July 2025 - August 2025
Hawkins Pond & Macdonough Hall Brick Paver Replacement:
Campus Let Project
Bid Process: Complete
Construction: July 2025 - August 2025
Ward Hall Counseling Center Improvements:
Campus Let Project
Consultant: AEDA
Design: October 2025 - May 2025
Bid Process: June 2025 - August 2025
Construction Schedule: August 2025 - December 2025
Myers Recording Studio:
Campus Let Project: CREST Grant
Consultant: Hyman Hayes Associates
Design: April 2025 - October 2025
Bid Process: November 2025 - January 2026
Construction: January 2026 - July 2026
HTHW Replacement - Priorities 1 & 4:
Campus Let Project
Consultant: RMF Engineering
Design: May 2025 - October 2025
Bid Process: November 2025 - February 2026
Construction: May 2026 - October 2026
ADA Study - Campus Wide
Campus Let Project
Consultant: MJ Design
Design: June 2025 - December 2025
Kehoe - ADA Bathrooms:
Campus Let Project
Consultant: Architecture +
Design: June 2025 - December 2025
Bid Process: January 2026 - April 2026
Construction: May 2026 - May 2027
Capital Planning is committed to enhancing & improving our campus.
CAPITAL PLANNING & CONSTRUCTION
40 Sanborn Avenue
101 Broad Street
Plattsburgh, NY 12901
(o) 518-564-5052
plattsburgh.edu <https://www.plattsburgh.edu/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/png
Size: 61858 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/png
Size: 115209 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 353197 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 64279 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment-0001.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 214296 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20250417/08c27bc7/attachment-0002.jpe>
More information about the Critical-Employees
mailing list