Parking Lot Project Update

[image: image]



[image: image]

Lots 27 & 28:

   -

   First 3 weeks have progressed well.
   -

   Existing Lighting has been removed.
   -

   Granite curb removal in progress.
   -

   Underground pipe inspection is complete
   -

   All catch basins should be installed by this Friday.



Lots 9 & 10:

   -

   Initial start has been tentatively pushed back until the week of Monday,
   May 27, 2024.
   -

   Contractor is focusing on Lots 27 & 28 to stay ahead of the progress
   schedule.



Capital Planning will continue to provide updates.

Thank you for your continued patience & understanding.






CAPITAL PLANNING & CONSTRUCTION

40 Sanborn Avenue

101 Broad Street

Plattsburgh, NY 12901

(o) 518-564-5052

plattsburgh.edu <https://www.plattsburgh.edu/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240515/2cc72621/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 92437 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240515/2cc72621/attachment.jpe>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/png
Size: 61858 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240515/2cc72621/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image
Type: image/jpeg
Size: 69778 bytes
Desc: not available
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240515/2cc72621/attachment-0001.jpe>


More information about the Critical-Employees mailing list