[Important Information for Employees] Update 9 | Loss of Heating Services in Residence Halls and Buildings
Office of the President
president_office at plattsburgh.edu
Tue Mar 5 18:21:56 UTC 2024
*The following message is being sent on behalf of Todd Moravec, Interim
Vice President for Administration and Finance*
Dear University Community,
Repairs have proceeded according to the plan summarized in the last campus
update
<https://www.plattsburgh.edu/about/offices-divisions/administration-finance/facilities-construction-services/heating-updates.html>
(#8).
This morning, heating services for most buildings along Rugar Street had to
be temporarily suspended to complete the reconnection of the six affected
buildings to the primary high-temperature hot water line. During that time,
we encountered an additional repair that currently appears to be minor but
is projected to delay the restoration of heating services until tonight.
Assuming repairs continue as scheduled and there are no additional
unforeseen circumstances, we anticipate the restoration of heating services
for all buildings along Rugar Street this evening, with temperatures
returning to programmed levels overnight.
The next comprehensive campus update is scheduled to be released no later
than 7 PM tonight.
Thank you.
Todd Moravec
Interim Vice President, Administration and Finance
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240305/cb5d9908/attachment.htm>
More information about the Critical-Employees
mailing list