[Important Information for Employees] Update 8 | Loss of Heating Services in Residence Halls and Buildings
Office of the President
president_office at plattsburgh.edu
Mon Mar 4 21:31:00 UTC 2024
*This message is being sent on behalf of Todd Moravec, Interim Vice
President for Administration and Finance*
Dear University Community,
The restoration of heating services to impacted buildings is entering a new
phase. Enough pipe was found on both sides of the rupture to weld in a
replacement section. This phase of repairs will take some time. Pending
unforeseen issues, we are currently on pace to restore heating services to
the impacted buildings by Tuesday afternoon. During the process of
restoring heat to the impacted buildings on Tuesday, other campus buildings
along Rugar Street will see a disruption of heating services.
The following buildings will continue to be affected for the remainder of
Monday (3/4/2024) and overnight into Tuesday (3/5/2024):
-
Clinton Dining Hall
-
deFredenburgh Hall
-
Hood Hall
-
Moffitt Hall
-
Sibley Hall
-
Wilson Hall
We have created a dedicated website that provides all campus updates
<https://www.plattsburgh.edu/about/offices-divisions/administration-finance/facilities-construction-services/heating-updates.html>
in chronological order. The next campus update is scheduled for no later
than 1PM on Tuesday (3/5/2024).
Your continued cooperation and understanding during this period are greatly
appreciated. We are committed to resolving the issue promptly and ensuring
the comfort and well-being of all those affected.
Thank you.
Todd Moravec
Interim Vice President, Administration and Finance
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://ls.plattsburgh.edu/pipermail/critical-employees/attachments/20240304/edfdfed4/attachment.htm>
More information about the Critical-Employees
mailing list